Saturday, November 7, 2020

Updates!

Old main room is now the girls’ room

Painted living room.
Our bedroom
Solar!
Framing of the mud room

 Giant south facing windows 

Finishing touches

Monday, August 24, 2020

Fully enclosed, working on insulation

All windows and doors are now installed with the exception of 3 custom triangle windows on the South side (on order, awaiting arrival).  Our bedroom is hung with insulation and sheetrock will be starting soon.  It won't be long before we can move into the bedroom area!!










 

Tuesday, July 28, 2020

Final rafters up, bedroom has 4 walls :)



Next, OSB, insulation and steel roof on the rafters.
Final wall up, and get a quote for spray insulation.

Tuesday, July 21, 2020

Monday, June 29, 2020

Walls are going up on the addition

It's moving quickly now!! Lucas has been hard at work whenever I have a day off getting the walls constructed! Really starting to feel real!





Hot shower

It's simple and efficient!
1) turn on generator
2) open water hose from gravity fed tank
3) plug motorized pump in
4) turn on propane
= on demand hot shower within 30s!

Thursday, June 4, 2020

Hot shower, new paint, prep for foundation, and new flooring

It's been a busy few weeks with some exciting changes!
Little Helper

Lucas built us a new "dining set"/picnic table :)
Green before

Gray after 



And a lovely new floor 


Framed in for the concrete to be poured for the 20' x 25' addition
I missed catching pictures of the new hot shot (on demand propane heater!!)  but it is luxurious.  Will try to capture soon.